Client: Public Services and Procurement Canada
Status: 93% complete

 

The Multi-Million Dollar Project Highlights Include:

  • Design, installation and removal of two 70m long cofferdams.
  • Design, installation and operation of a temporary water gate system.
  • Design, installation and operation of a temporary water treatment plant capable of handling 1,200 gpm and a holding capacity of 1,000,000 liters.
  • Demolition and removal of 1,800 cubic meter concrete dam with two winch operated stoplog sluices.
  • Installation, testing and commissioning of a 3,200 cubic meter concrete dam and gate system.
  • Removal and reinstallation of a 100 year old stacked stone wall.
  • Site remediation and landscaping of 4,200 square meters of Federal Park within a Parks Canada National Historic Site.