The West White Rose Project in Argentia, NL reached a major milestone in October. This time-lapse shows continuous concrete pours for each quadrant of the concrete gravity structure’s base:

  • Northwest Quadrant: April 20th to May 24th
  • Southeast Quadrant: June 8th to July 6th
  • Southwest Quadrant: August 8th to Sep 5th
  • Northeast Quadrant: September 20th to October 18th

 

Pennecon is thrilled to be a part of the team bringing this important project to new heights. Congratulations to the SNC-Dragados-Pennecon General Partnership! 👍

Learn more about the project at http://wwrp.huskyenergy.com/