CLIENT: Wood PLC
STATUS: ONGOING

Pennecon Hydraulic Systems (PHS) and Palfinger Marine are supplying the four gantry cranes for the Husky West White Rose Project. These cranes are for the well bay and intervention areas on the platform and have a 30 metric tonne capacity and Class 1, Zone II certified for hazardous area. The cranes are currently in final assembly in the Palfinger Marine Facility in Gdynia, Poland and are due for delivery in April/May of 2019.

The client for this project is Wood PLC with the end User / Operator being Husky Energy.